 Results - Diamond Mine

Context / scope of project: This underground mine was having problems with their outsourced mining contractor and eventually needed to change them out without causing major disruptions to the operation of the site. PIP’s involvement was to try to salvage the performance of the existing contractor, but also plan for a change if needed, then oversee the contract replacement.

PIP and client achieved:

weekly underground development up 50% within 2 weeks of transition (105 to 157m/week)

minimal disruption
all required equipment ready on first day of new contractor

new contract more commercially favourable

all existing contract labour interviewed within 4 days of announcement of change



 

 

Back to top  |  Back to 'Our Results' page     


Back to 'Our Results' page
  

What we did:

mediated between company and original contractor
found alternative contractor as a standby
negotiated commercial terms with new contractor
planned in detail contract takeover (including risk assessment for new contractor)
developed and managed 30 day plan to ensure smooth transition


 