| Iron Ore Developing Nation |
PIP was engaged to optimise capital expenditure on
major Greenfield iron ore development project during
the pre-feasibility study. The project was for a large
scale operation in a developing world context, where
major new port and rail infrastructure would be required
to support the new mine operation and the export and
shipping of the iron ore. The goal of the prefeasibility
study (PFS) was to develop an option to produce a large-scale
output for a positive project NPV from the identified
resource. The project design or base case to achieve
these goals is only determined at a conceptual level
in the previous phase of studies, thereby making the
study of alternatives of critical importance.
Using NPV as its guide, the PIP ROCX process identifies
the drivers of value and then systematically identifies,
prioritises and assesses ways to reduce capital, risks
and operating costs, and to increase revenue and time-to-first-profit.
The main objectives of the PIP team on this project
at prefeasibility stage (PFS) were twofold:
- Systematically conduct a comprehensive early stage
assessment of design and technology alternatives for
the operation in order to maximise the project NPV
and lead to a set ‘base case’ design for
future study phases. This involved excluding options
that were not commercially viable. (See Chart One.)
This phase included ‘macro’ options which
had fairly significant NPV effects and downstream
design implications as the optimal production tonnages
for the mine, as well the products produced and the
process flow sheets.
Several new technologies were also assessed to determine
their NPV impacts and the likelihood of technical
readiness for the start of mine operations. Some of
these technologies such as tubular modular track,
continuous miners and regenerative conveyors have
high value-adding potential.
- Drive the commercial evaluations and capture technical
evaluations of the ‘base case’ operational
design including assessment within the areas of rail,
port and mine to produce an ‘optimised case’.
This phase included mine to port simulations on product
flow as well as NPV impacts of the freight strategies.
A more systemic advantage of having the PIP team in
place was the benefit to the integrated planning on
the project – by eliminating the functional silos
that can sometimes exist. Individual experts and managers
for different functional areas were brought together
to communicate not only the options under consideration
in their area but also the options under consideration
in other areas that may impact their own planning and
require flexibility of design in their area.
The ROCX methodology involves steps which apply at
each design stage not just at PFS stage (business case
through to detailed design) with the steps being applied
with increased level of detail in the later stages of
the design compared to the early stages. These involve:
- Identifying the levers which drive NPV.
- Determining the range of NPV impact each lever
could have.
- Generating ideas on ways to reduce the downside
impact and increase the upside impact of each lever
on NPV.
- Stress testing the viability of the ideas –
starting with those with the highest ‘value:ease’
to focus efforts on the highest potential impact ideas
first.
- Systematically refining the strategy and design
as the viability of improvement ideas firms up.
At a conceptual level the process systematically reviews
each lever to drive the NPV outcome. For further information
on the ROCX methodology, please contact PIP for our
article on our ROCX methodology. |